DAY 1
The first day is exciting. Our crew arrives with the equipment to get the project under way. We start with the layout of the pool, then begin the excavation. We end the day with the installation of the base materials. You will be able to look out and imagine what it will look like once completed.
DAY 2
Your pool arrives on location and is lifted into place! Great care is taken to level the pool with laser guided equipment. You are now the proud owner of a swimming pool, but not quite ready for diving in just yet!
DAY 3
Now it's getting real! The plumbing is installed and your new pool is filled with water. It sparkles as the sun races across the top and you are already anticipating the hours of enjoyment in your pool. After the pool is filled, the pool level is again checked to make sure no movement has occured.
DAY 4
Pool coping forms are installed and the pool is backfilled against the wall. Forms are built for the surrounding concrete and preparation is made for the pour.
DAY 5
The concrete crew arrives and the concrete is poured. Finishers put the magical touch to the surface.
DAY 6
The final day arrives and the crew is on scene to finish the job. The concrete forms are pulled and the pool is cleaned and made ready for use. Your amazing dream pool is ready for your friends and family to come over for a pool party!